Where should a new waste incinerator for Antwerp be built?

The City of Antwerp wants to investigate whether alternatives are possible for processing its residual waste, and where they could be located. This currently takes place at the ISVAG site in Wilrijk, but the permit was due for renewal. Antwerp therefore called on VITO to organise and oversee a market consultation, with a view to reaching a concrete, workable conclusion. This consisted of two parts. The first was to consider the best possible solution for processing residual waste. The second was to look at the options for heat production. The permit has since been renewed, but the controversy has by no means died down. We therefore set out the report’s main conclusions below.
The City of Antwerp’s residual waste is currently processed by incineration with energy recovery at the ISVAG facility. In addition to waste from the City of Antwerp, residual waste from neighbouring municipalities is also brought there. However, the facility’s permit is nearing its end. A new solution must be in place by 1 January 2026. ISVAG plans to build a new incinerator at the same location, with an annual capacity of 190,000 tonnes. It will also supply electricity to the grid and heat to businesses and a residential area in the south of Antwerp. Through an RFI (request for information), the City of Antwerp wanted to find out whether alternative scenarios were possible, not only for processing the waste but also for meeting the commitments already made regarding heat production. VITO therefore conducted a market consultation in two stages: first, identifying interested market players and exploring their proposed scenarios, followed by a second round in which a selection of market players submitted detailed information.
Alternative site in the Port of Antwerp
All shortlisted suppliers of proven technology agreed on the same approach. They proposed building a new waste incineration plant at a different location, namely in the port. The technology they would use is the same as that envisaged for the future ISVAG site. The advantage, however, lies in the opportunity to use the steam produced directly in nearby industry in the Port of Antwerp. Compared with converting it into electricity or heat, as proposed by ISVAG, this is a more efficient use of heat. A crucial condition is that the steam is recovered from waste processing rather than generated through a conventional process using natural gas and fuel oil. This would avoid more CO2 emissions than the ISVAG scenario. An analysis of processing costs shows that the alternative plants would involve lower capital costs and generate higher revenues from energy recovery than ISVAG.
Additional investment in a transfer station
There is also the logistical aspect, a contentious issue in and around Antwerp, where the ring road is often congested. To transport the waste to the plant in the port without adding to the impact, investment would be needed in a transfer station. The suppliers propose building it at or near Blue Gate and transporting the waste to the port by lorry, train or boat. This would add €5 to €25 per tonne of waste, but further sorting bulky waste, either at the transfer station or at a dedicated site, could reduce the amount requiring incineration by 5%. Several suppliers also suggested limiting the plant’s capacity to 160,000 tonnes. Any capacity shortfall could be covered by signing an additional contract to process the extra waste at other plants. This would encourage the city to pursue an active policy to further reduce residual waste in the future and prevent a lock-in that would require waste to be brought in to meet the commitments under planned heat or steam contracts.
Heat supply cannot be fully replaced
Finally, there is the demand for heat in the south of the city. There would no longer be any heat sources available there. One proposal was to build a sewage sludge incineration plant at the Blue Gate site. It could incinerate around 160,000 tonnes of wastewater treatment sludge per year, brought in from across Flanders. After further processing abroad, the resulting ash could provide a source of recovered phosphorus. Heat pumps could also be installed at the wastewater treatment plant at Blue Gate. The combination of sludge incineration and heat pumps could meet the heat demand of Cluster Zuid and Blue Gate. In that case, there would be no need to invest in the planned heat collector, but heat would cost more than from ISVAG. It would not be possible to replace all of ISVAG’s potential heat supply. This would require an expansion of the backbone carrying residual heat from the port to the south of the city. Neither the timing nor the implementation of this has yet been decided.