Two powerhouses make short work of old bridge
Text Roel van GilsImage SAES

Demolishing a bridge takes more than brute force. During the demolition of the existing structure over the watercourse alongside the N561 provincial road in Noordwelle (Zeeland), two Epiroc breakers supplied by SAES showed their muscle. Sinkegroep carried out the complete demolition in a controlled, precise manner, with minimal disruption to the surrounding area. The existing structure was expertly removed to make way for a precast box culvert.
Late last year, Gebr. De Koning B.V. invited Sinkegroep to tender for the demolition of the bridge over the watercourse on Stoofweg. The tender led to a successful collaboration and, ultimately, the contract for the complete demolition. During the work, Sinkegroep was able to demonstrate its capabilities: using two excavators, the entire structure was demolished in a controlled manner and on schedule.
Maximum control
For a job like this, choosing the right combination of machine and attachment is essential. Sinkegroep opted for two Epiroc breakers from SAES. The breakers deliver the impact force needed to break concrete structures in a controlled manner, while giving the operator sufficient control over where and how the material fractures. The Vibrosilent Plus system also helps reduce vibration and noise for the surrounding area. Epiroc breakers use hydraulic pressure in combination with a nitrogen chamber. The nitrogen acts as a spring for the piston, generating high impact energy with each cycle. This makes the breakers suitable for a wide range of demolition work, from concrete and reinforced concrete to asphalt and rock. For Sinkegroep, that means reliable equipment that delivers what is needed during an intensive demolition job.

Official opening
After the demolition, the site was prepared for installation of the new precast box culvert. The work was part of a larger project around the N651. The road was temporarily closed to motorised traffic, and a temporary diversion including a cycle bridge was put in place for cyclists. At the same time, a new roundabout and a cycle tunnel were built near the Dammenweg-Stoofweg junction. The project came to an end with the official opening of the new bridge at the end of May 2026. For Sinkegroep, it is a great example of how the right people, machines and attachments combine to deliver a controlled and efficient demolition.
Looking for precision demolition?
Call SAES. Epiroc breakers are designed to break concrete structures, asphalt, rock and reinforced concrete, among other materials. With models available for a wide range of machine classes, there is a suitable breaker for almost every demolition job, whether for hire or purchase. For the mini and midi ranges, Epiroc offers the SB series in the Solid Body concept, with unnecessary components removed to create a more compact and lighter design. From the MB series upwards, advanced protection systems are available to prevent blank firing and limit vibrations transmitted to the excavator. SAES Epiroc breakers are available for excavators weighing 0.7 to 140 tonnes.
Een zakelijke vraag aan Saes International BV? Get in touch
Companies in this story
Keep following this
Get an email when a new story is published. No account needed.
- ThemeCircular construction and demolition
- SubjectAttachments
- CompanySaes International BV




















