Circularity a priority in the conversion of the Fritz Toussaint barracks
Text Valérie CouplezImage Ekkow Photography

BIM model guides circular deconstruction
From gendarmerie barracks to a new, open, multifunctional neighbourhood. The Usquare.brussels project aims to transform the Fritz Toussaint barracks in Ixelles into a vibrant mix of family homes, student accommodation, university facilities and businesses. No longer a closed military complex, but an entirely new urban district with all that entails. Coordination is being handled by MSI (Maatschappij voor Stedelijke Inrichting), which is setting high sustainability targets and pursuing circular deconstruction.
In 2018, the Brussels-Capital Region bought the 3.9-hectare site of the former Fritz Toussaint barracks in Ixelles from the federal government. The aim is to give the landmark buildings, which cover a total area of 56,000 m², a new lease of life and create a unique blend of history and the future. That, at least, is the mission envisaged by coordinator MSI. Project manager Ann-Sophie Doesburg and architect & urbanist Bruno Allardin: “We want to create a project that captures the site’s more than 100-year history, while also laying the foundations for the next 100 years.”

Sustainability as a guiding principle
From the outset, MSI set out its ambition to make the project as sustainable as possible. The focus is therefore on restoring the buildings to their original state wherever possible, while keeping their future use in mind. That use will be future-proof, with the new structures designed to allow for flexible adaptation as needs change. Buildings will only be demolished rather than renovated if their structural stability is inadequate. “The principles of circular deconstruction and construction run through this conversion project. Recovered materials will be given a second life on site wherever possible. If that is not feasible, we will look at where else they could be used or how they could be recycled to a high standard. If new materials are needed, we will choose products with the lowest possible impact. Think, for example, of clay and hemp for insulation.”
Partner in circularity
To give this strategy the necessary impetus, MSI issued a public tender for support. Rotor won the contract and received a budget of 170,000 euros to help define and implement a circular strategy over four years. The plan was to create a BIM model linked to a reuse inventory. Doesburg and Allardin: “By bringing together information about the available materials, it would be easier for the architects, engineers and contractors involved to give them a second life. This gave all project stakeholders access to data on dimensions, quantities, composition, location on site and physical properties. It also provided a basis for assessing the strategy against economic, technical and environmental indicators.” Each use was accompanied by an average of around twenty pages of materials inventory.

BIM model lays the groundwork for circular deconstruction
It was decided to create a BIM model only for the buildings earmarked for renovation. “The intention was for the model to remain useful throughout the building’s life,” explain Doesburg and Allardin. Rotor provided thorough training so that all stakeholders, including the architect and contractor, could work with it. Using the materials inventory and BIM model, two scenarios were assessed for each building. Rotor managing director Lionel Billet: “Should we try to preserve as much as possible, or is a major renovation necessary? We look at the impact of each scenario in terms of maintenance, the need for reused materials, and the quantities of materials that would become available for reuse or recycling …” The scenarios clearly showed that circular deconstruction and reuse were viable options.
A complex exercise
So the work began, but not without its challenges. Rotor may be a pioneer in circularity, but it did not yet have experienced BIM specialists on its team. “That meant the process took longer. At the request of the team building the BIM model, we regularly returned to the site to take additional measurements. And while it contained too much detail in some areas, making the deconstruction process more complex, it was not detailed enough for reconstruction. This ultimately resulted in several BIM models, even though there would be considerable benefits if the BIM model for reuse could also be used by the architects and construction team. All stakeholders therefore need to communicate in advance about the level of detail they require to prepare more effectively. The intention, however, is to integrate the BIM models created into a single as-built BIM model that can be used throughout the life of each building,” says Billet.

Central hall used for storage
Despite the challenges, the BIM model was invaluable in enabling the buildings on the site to be deconstructed circularly and the recovered materials reused. “Because the site was a complex maze of buildings, the BIM model was the perfect guide to finding exactly where the elements suitable for reuse were located and how much storage space we would need.” Part of Building M, centrally located on the site and later to be repurposed as a covered hall for sustainable food, was set up as a storage area and marketplace. This is where, among other things, bricks from demolished buildings were stored for use in new structures. The information was readily accessible to both the contractor and interested parties.
Expectations exceeded
“We also used BIM to estimate the volumes of reusable materials and waste that would be generated. This provided a basis for the scenarios we developed, and also helped us set minimum requirements for reuse and recycling.” The requirements specified not only the minimum quantities of material to be recovered for reuse or recycling, but also the quantities of second-hand materials and recycled materials to be used in the renovation. “These were minimum thresholds,” say Doesburg and Allardin. It was then up to bidders to devise creative ways of meeting the criteria. “The thorough preparation made possible by the BIM model meant that our expectations in this respect were far exceeded. We received proposals that were ambitious, but still in line with the realities of the building,” Doesburg and Allardin add.