Biostoomcentrale Beringen: full steam ahead!

Waste becomes a resource
This pithy saying aptly sums up the core activity of the new biomass power plant built by Biostoom Beringen in the West-Limburg industrial zone in Beringen.
Work on the plant began in 2018. Today, the project is complete and the plant is operational. From now on, 200,000 tonnes of residual household waste from Limburg and comparable commercial waste will be converted into thermal energy (steam and hot water) and electricity each year through environmentally friendly and efficient incineration.
Sustainable energy, then, that fits into the broader vision of a better, cleaner environment.

The start was difficult. Spring 2018 was very wet, making it hard to prepare the site for construction, while the initial foundation work was no easy task either.
After that, however, work proceeded to schedule. The engineers had the opportunity to bring together the best available techniques and the latest technology in one powerful facility. One example was the waste bunker, built using slip-forming. The contractors managed to raise the structure to a height of 36 metres in just 12 days.
The incinerator grate comprised metal modules weighing 62 tonnes, transported from Switzerland in 2 convoys of 4 lorries each. Installation of all the components went smoothly, and most of the work was completed within 3 days.

State of the art
The result is a biomass power plant that is state of the art, built to the highest technological standards currently available.
The plant processes 200,000 tonnes of non-hazardous, non-recyclable waste each year.
This consists mainly of household waste and comparable commercial waste.
Incineration produces thermal energy, which can be supplied to the immediate area via a heat network in the form of steam or hot water. Petrochemical company Borealis, the plant’s neighbour, is already a first and very important customer for the heat network.
The remaining available energy is converted into electricity.
Question about this story? Ask your question
Keep following this
Get an email when a new story is published. No account needed.
- ThemeImproving waste collection and transport
- SubjectNews