Through the GO4ZERO project, Holcim aims to produce decarbonised clinker and cement from 2029. Before the end of the decade, all CO2 from clinker production at the Obourg site will be captured for geological storage (CCS) in the North Sea. The complete transformation of the industrial site, planned in two distinct phases, marks a key step towards decarbonising our cement industry.
GO4ZERO goes beyond safeguarding Holcim’s local cement production capacity for the Benelux and northern France markets. Its aim is to make a significant contribution to decarbonising the Belgian construction industry in these markets.
At the heart of the project is the Obourg cement plant (Mons), a historic site where cement production has continued for more than 110 years. The project is being carried out in two phases. The first began in January 2024 and is expected to be completed around 2027, while the second is due to be completed by 2029.
In terms of the circular economy, Holcim, the developer of the G04ZERO project, already has extensive experience in the co-incineration of waste, as Stany Vaes, Director of Sustainability & Corporate Affairs at Holcim, explains: « In our kiln, we use co-incineration, which means that we use waste both as fuel to reach the high temperature of 1 400 degrees and as raw material, since the residues from combustion end up in the final product, clinker, as a raw material. In addition, the kiln acts as a filter because it breaks down all the PFAS contained in the waste. These then bind with the product, so they no longer end up in the air, water or dust. A fine example of circularity and, in part, a solution to the PFAS crisis ». But, as noted, the project’s environmental ambitions go much further.

GO4ZERO, phase 1
In the first phase, the existing kiln is being replaced with a completely new dry-process kiln based on the most advanced technologies, delivering unprecedented operational and environmental performance. It uses a material with a much lower water content, limestone, which is available in large quantities in the quarries of Tournaisis. The thermal energy requirements of the dry process will immediately be reduced by 40%, resulting in an immediate 30% reduction in specific CO2 emissions.
GO4ZERO, phase 2
The second phase includes the installation of an innovative oxy-combustion process in which oxygen replaces air. This process will concentrate CO2 in the exhaust gases to more than 80% (compared with 30% in phase 1). This change will necessarily go hand in hand with the activation of the carbon value chain: purification on site to more than 99%, pipeline transport, liquefaction at the Antwerp terminal and loading onto ships, maritime transport and storage in the North Sea. This chain is expected to be operational by mid-2028, making carbon neutrality from 2029 a possibility.

Circularity in the spotlight
With more than 95% of its thermal energy needs met by alternative fuels and more than 30% of its raw materials coming from partially decarbonised industrial residues or by-products, the project is already an example of circularity. Significant investment is also planned in parallel to generate energy on site, meeting up to 50% of requirements, notably through the construction of a floating solar farm and the installation of a heat recovery system at the kiln outlet.
Of course, delivering a project on the scale of GO4ZERO requires the mobilisation and coordination of a broad range of expertise. To make this happen, collaboration between the public and private sectors is essential, spanning activities that include defining environmental objectives, technical development, financing and obtaining the necessary permits. « There is no doubt that, with the support of the public authorities and our various partners, this ambitious pioneering project can be completed within the proposed timeframe », says Stany Vaes with great enthusiasm.